HSK Sähkö Oy

Jokela’s wind farm

Jokela’s wind farm will have a twelve wind turbines and the total power is 36MW. The constructor is WPD Finland. The construction work has just started. The wind park rises from the center of Kalajoki about 4km to the north. The size of the whole project area is 300 hectare. HSK Sähkö Ltd. builds the 20kV electricity and fibre cable network on the wind farm of Jokela.

The construction work started in April 2014 and it will be finished at the end of 2015.

Jokela’s wind farm. Kalajoki (WPD Finland)

Year: 2014 -2016

Customer: WPD Finland