Kopsa II wind farm
Puhuri Ltd. constructed the Kopsa II wind farm in Raahe. Farm’s total nominal power is 33 MW; there are ten 3,3MW Vestas V126 wind turbines. HSK Sähkö Ltd. produced the wind farm’s 20 kV subterranean cabling work and installation and also the fibre cabling to all ten wind turbines.
The second phase of Kopsa wind park construction work started in 2013 and the installation works were finished in autumn 2014.
2014 Kopsa II wind farm: high voltage cabling, Raahe (Puhuri Oy)
Year: 2014
Customer: Puhuri Oy